Now, when the Scan Using Scanlogic button is set to YES, the Start date/time and End date/time fields will need to be completed.
We've also added a new validation to ensure that the End date/time of the activity must have a value greater than the Start date/time, helping to improve activity setup.
To configure this option, please follow these steps:
- Open Participantlogic and select a project.
- Click on menu option Maintenance navigate to Activities.
- Scroll down to the Scan Using Scanlogic button and select YES.
- Complete the Start date/time and End date/time fields.
- Finally, save changes.
To see a screenshot of these steps, please click here.